A. All construction or modification of wastewater facilities, whether under permit, agreement with the City, or City contract, shall be inspected by City forces during construction so as to assure full compliance with approved plans, specifications and details, in addition to adopted City standards as referenced in CVMC 13.08.030.

B. No person other than duly authorized employees of the City shall backfill any trench or excavation made for the purpose of constructing a wastewater facility until the pipe or structure therein shall have been inspected by the Director and written approval has been given in such form as may be determined by the Director. The entire length of pipe shall be fully exposed for inspection. At least 24-hour notice shall be provided in advance of such sewer inspection.

C. The Director may employ such tests as deemed necessary in testing sewers and other wastewater facilities. The contractor shall furnish all tools, labor and assistance necessary for such tests. (Ord. 2466 § 7, 1991).